Stage 3: Start of Project Feasibility / Business Case
Legal Advisors Appointed
No
Financial Advisors Appointed
No
Technical and Other Advisors (inc Project Preparation Facility) Appointed
No
Is a Business Case Being Prepared?
Yes
Business Case Prepared By
Government
Preparer company/department name
Tucepi Municipality
Estimated Business Case Completion Date
Q1 2018
Estimated Time To Start Of Procurement
Unable to be estimated at this time
Any other relevant information relating to the project process
The preliminary design needed for future location permit has been completed. The Environmental Impact Study has been finished and submitted to the Ministry. The Decision on port area border (nautical port) has been issued in accordance to the Urban Development Plan.
The Split-Dalmatia County announced a Decision on intention to issue a concession on maritime domain for construction and usage of the nautical tourism port Lucica in Tucepi. The company Tucepi Ltd. (100% owned by the Municipality of Tucepi) will participate in the tender. In case that Tucepi Ltd. is selected as a concessionaire, a potential investor will be able to enter the project as a sub-concessionaire.